40 M Span Bridge & 16M Elevated Water Tank @ Seremban


Project Info

Completion
October 2022
Scope
VE proposal for micro piling to to driven precast spun piling for bridge & bored piling foundation to driven precast spun piling for water tank
Client
Aligan Industries Sdn Bhd

Project Title : Tempat Simpanan Air Untuk Cadangan Membangunkan (Fasa1) 8 Block Pangsapuri Prima (25 Tingkat) Berserta Kemudahan Di Atas 5 Tingkat Podium Tempat Letak Kereta Di Atas Tanah Kerajaan Lot 3902, Mukim Bandar Seremban

Needs : Client faces time & cost challenge for water tank foundation using cast insitu bored piling foundation

Problem : Higher cost & longer construction duration for original cast insitu bored piling foundation design for water tank

Solution : The problem solve when VE was done to convert the cast insitu bored piling foundation to driven precast spun piling with lower cost and shorter construction period

Saving : Approx. RM 350,000.00 or 70% for bridge piling & RM 150,000.00 or 20% for water tank piling